The task timeline brings together scheduled task periods and projections for recurring and contract-based tasks. It is a viewing tool: viewing the timeline, applying filters and hiding projections do not change tasks or resource allocations. A bar represents a planned or estimated period, not actual hours worked.
Open the timeline
In your browser, open Work management and select Task timeline from the toolbar at the top of the page. The timeline has its own filters and settings; the Work management main filters and saved views are separate.
You can also display the timeline on the Dashboard. Open Control dashboard and select Task timeline from the Widgets list. For instructions on arranging panels and saving the layout, see the Dashboard panels guide.
In the Work management task list, you can also click a linked responsible user's name and open the Task timeline section in their user information. The name is a link only if you have permission to view the user's information. This timeline is limited to that user: responsible user and responsible role selections are not offered, and only their allocated periods are shown.
The timeline shows only information that your permissions allow you to see. Visibility also depends on permissions for the task's Spot and, for contract projections, the contract and projected task. The Android and iOS apps have their own task and calendar views; the timeline described here is opened in a browser.
Filter and organize the view
Use the preset selector in the timeline toolbar to select a saved preset or Built-in defaults. Open Settings to define the date range, task filters and display options. The Devices, Folders and Customers quick selections in the timeline toolbar narrow the search without saving changes to the preset. When a quick selection has a value, it replaces the saved filter for the same field in that search; clear the quick selection to return to the saved filter.
In the Task filters section, you can filter by task name, devices or Spots, folders, customers, contracts, categories, responsible users, responsible roles, statuses and priorities. Folder and customer filters include subfolders. If you select both responsible users and responsible roles, a match with either is sufficient. The built-in status selection includes Open, Late, In Progress, In Review and Completed.
In the Date range section, select Rolling to calculate the period from the current day using the selected numbers of days and months, or select Fixed dates and enter a start and end date. The date range can be no longer than one year. In the Display section, you can select a daily, weekly or monthly scale, sort by the earliest visible bar or task name, and show or hide the legend and today's marker. Use Group by in the toolbar to group rows by device or folder.
The built-in preset shows a rolling period from 14 days ago to two months ahead, at a daily scale, with the earliest visible bar first. The legend, today's marker and both projection types are enabled. On the timeline in user information, the built-in period starts seven days earlier. In other places where the timeline is used, a previous selection or a shared default preset may be applied instead of the built-in defaults.
Save a preset
In the Settings window, enter a name for the preset and select Save or Save as at the bottom. Saving an editable preset updates it everywhere it is used. Save as creates a copy; also use it when the selected preset cannot be edited. Saving requires the necessary permission.
When saving a new preset, an administrator can select Shared preset or Shared default preset. In the preset selector list, a trash icon appears next to presets that can be deleted. Deletion requires delete permission, and the shared default preset is protected from deletion by anyone other than an administrator. Deleting a preset does not delete tasks.
The selected preset is remembered separately for each place where the timeline is used. The Dashboard panel also remembers the selected preset as part of the panel layout. Saved timeline presets are separate from saved Work management views.
Interpret the bars
For an existing task, valid resource allocation periods that overlap the search range are displayed. If a task has resource allocations, a fallback estimate is not created from its due date, even if the allocations are invalid or fall outside the selected date range. In a user-specific timeline, another person's allocation is likewise not converted into a due date estimate.
If a task has no resource allocations at all, the bar is estimated from its due date and planned duration. The duration is divided by the Hours per calendar day value in the General section and rounded up to whole calendar days, ending on the due date. The default is eight hours, and the allowed value is 0.5–24 hours. For example, 17 hours of planned work produces a three-calendar-day bar with the eight-hour setting. If there is no positive duration, the due date is displayed. Without a due date, this estimate cannot be created.
Hover over a bar to see the times, Spot, categories, priority, status or projection indicator, and the source of the timing. At a daily scale, a bar for a single day visually fills the day's cell; you can see the exact times in the details. The status color of a completed or late task takes precedence over the category color. You can set category colors in the Category styles section of the Settings window.
Click a bar or task row to open the task. If there are several overlapping periods, you may first see a list of them. A projection bar may open an existing source task; this does not mean that the future task has already been created. If there is no source task, the view indicates that the occurrence is a projection.
Understand projections
In the Projections section, you can show or hide Recurring projections and Contract projections separately. A bar with a dashed outline is a calculated future occurrence, not a created task. Clearing the selection hides the projection without changing tasks.
A recurring projection is calculated from the last task in the recurrence chain that your permissions allow you to see. That task must also match the timeline's other filters. The calculation takes the recurrence end date and maximum number of occurrences into account and does not invent past occurrences. A completion-based recurrence is indicative: the projection assumes the task will be completed on its due date. For more information on recurrence settings, see the recurring task guide.
A contract projection is based on the task settings of a contract that creates tasks and the next saved creation date. The projection is calculated for applicable Spots; an existing task with the same contract task setting, Spot and due date replaces the corresponding projection. Past occurrences are not invented. The projected period is based primarily on the resource allocation settings of the source or task template, then on the default allocation if needed, and finally on a due date estimate.
Check the result
Compare a known task with its resource allocation times or, if it has no allocation, its due date and planned duration. Check the selected date range, statuses, other filters, quick selections and permissions. If an allocated task is missing from a user-specific view, check in particular whether the period is assigned to that user.
The timeline loads 100 rows at a time. If Load more appears, select it to see the next rows. The view also reports the number of omitted tasks and any invalid or overly broad recurrences. A missing due date or exclusively invalid resource allocation times can cause a task to be omitted. If necessary, correct the source data and select Refresh in the timeline toolbar.
To change planned resource allocation times, use the Work management Gantt view. It is a different view from the timeline described here.